Furnishings and workstation installation on the 6th and 7th floors of Citizen's Tower were underway as of Friday, January 24th.

A City of Lubbock press release says that the last installment of furniture for the Tower is scheduled to be delivered the week of February 3rd.

Vehicular and Crosswalk pavers also continue working at the intersection of Avenue K and 14th Street. Pedestrian walkways in the plaza are also near completion.

Metal panels are being installed on the outside of the Tower, and they're all expected to be in place by the middle of February.